SATURDAY, MAY 14, 2005
The tile and coping work took two days and was finished on Saturday, May 14th. Again, skilled craftsmen at work and the process was interesting to watch. They were very particular about matching tile batches since the color varied from box to box and they took their time to get it right. When they were done the electrician came to hook up the power, add breakers to our box in the basement and test the lights, the pump, etc. Everything was AOK.